Thurs 8th / Fri 9th - It's all go!
Two very busy days which included the preparations for our high safety wires annual service, followed by the servicing the next day. With the Works through road emptied it was also an ideal opportunity to swap the locations of the four coaches currently being worked on.
We had 17 staff attending on Thursday and 9 on Friday.
**************
Thursday
Not a good day for weather with on and off drizzle followed by heavier rain later. Dinmore Manor looked good though on the first train of the day.
The tool vans and tank wagons have now been moved for display at Toddington. It's been a long time since the Works siding was clear.
Paul and Dennis were cleaning the interior of BCK 21092, unusually stabled on the Cotswold side of the yard. Although a wet day at times, it was still humid. Dennis has a breather while Paul suddenly apoears in the corridor, having vacuumed the guards compartment.
Both vestibule ceilings were very grubby. Dave cleaned them, but a repaint was still needed, so Bob K. undercoated both. North end above, south end below. In the latter Dave is sorting out a bit of loose draught excluder in the doorframe.
Now a series of photos taken by Roger where the Indoor Gang were repairing more internal window frames in TSO 4772
4772 is located over in the far siding, now a mix of coaches from Rakes 3 and 4.
Geoff then attaches the plyboard below the window.
Finally a fresh bead of sealant.
The completed job. There were two pieces prepared on the paintshop trestles, so another window would have been similarly treated. Yet another has appeared on the trestles to be fully painted.
Back in the Paintshop Rex is doing some adjustments to the new lithium battery box under RBr 1675.
Richard II commented that he must seem to be forever working in the main control and distribution panel. To me it looks very complex, but he assures me that it's all quite simple really.
It's great to be able to really get going in 1675's corridor. On Tuesday the ceiling was primed. Today Jeff makes a start on the outer wall.
Into the Barn and progress with SO 4790. The Malvern side north end doorway with the filled and sanded doorframe and lots of dust to vacuum up. A coat of paint will soon transform this.
On one of the windowsills in Upholstery, the completed headrests for the FODR that were being worked on by the team on Wednesday.
*************
Friday
The weather on Friday was in complete contrast to the previous day and couldn't have been better for the day's activities.
With our overhead system contractor due soon, it was time to get all the through road vehicles out of the Works. SO 4798 and FK 13326 had gone from the Barn and Workshop respectively, leaving the MICA van and 1675.
With Stu driving and Clive as shunter, the 03 slowly backs towards the Works, ........
........ into the Barn and Workshop, ........
........ and picks up the MICA van.
Phil and Richard I discuss the planned flushing and sterilizing of the water tanks.
The 03 is back to collect 1675. Clive directs Stu as the buffering up takes place.
1675 heads out towards the light.
With 1675 disappearing outside, the view through the Works. Yuk, it looks a mess.
The worst bit is where the MICA van has been, but then again look at the work that has had to be done on it.
Nothing than cannot be sorted out with brush and the large vacuum cleaner. Both rail troughs were full of all sorts of things and needed a complete cleanout.
Great progress, always nice to have a shunt and clean things up .
ReplyDeleteAre you sure that the 3rd picture is RMB 1808? RMB's were not Brake end vehicles in BR days, and there is no mention of a heavy rebuild in its write up.
Malcolm in Canada
They may well have cleaned the RMB, but Paul and Dennis are indeed pictured in BCK 21092 there, well spotted!
Delete