Posts

Weds 25th / Thurs 26th - Very productive

Wednesday

Another great set of photos covering the day's activities - many thanks Gerry.

The underwindow panelling repairs on TSO 4867 have now reached the southern half on the Malvern side and well on the way to completion.


Nick begins removing corroded panelling on the first of the four remaining windows.


A very handy straight edge firmly clamped to the side of the coach.


Nick cuts out the unwanted section.


The replacement section measured, cut with the plasma cutter, and then positioned on the bodyside ready for welding.


On to the next window where Bob is removing the frame, which he takes to the windows bench for cleaning up.



Then back to the coach side to clean up around the window void.



Simon and Neil are preparing the north vestibule area ready for the replacement internal wall.


Ken making templates for the corridor connection brackets for the south end of TSO 4406.



Trevor working on the door removed from 4406.





Ceri, Laura and Eve re-covering another seat.


Chris with another batch of moquette keyrings.

**************

Thursday

Another varied day. Thanks to Roger for the extra photos.


Laid out on one of Upholstery's tables, the five brake coach keyrings now completed and ready for use (see Tuesday's posting).


Following on from yesterday, part of what will be the new north vestibule wall in 4867.


Also following on from yesterday, Gerry runs the grinder over the welds on Nick's new section of underwindow panelling.



Rex sands more internal window framing from 4867 before bringing it through to the Paintshop for preservative, dyeing and varnishing.


Alan cuts out the corroded area above the corridor at the south end of TSO 4406.



Over to SK 25451 where Phil is checking the bolt holes for the grab handles. In one the captive nut had gone, but we have a way of fixing this without having to remove the back panel.


Jeff repainted some of the panels in the toilet compartments (they are too cramped for me to take any photos of him working). He then moved to the seating compartments to varnish the base sections of the window frames.


Martin and later myself completed the tidying up of the backs of the doors. Any paint on the veneer was removed and the wood rubbed with wood dye. 


The backs were then given a fresh coat of varnish which really brought them up to standard again.



Discussion time with Paul, Roger and Alan who had had a busy morning, Paul in Rake 3, and Roger and Alan (and Geoff) in Rake 1 which is currently stabled in Platform 2.

The following five photos taken by Roger show the Indoor Gang involved in a number of repairs in the rake, including fixing loose tables, seat sides and tightening a loose sliding door. They do a great job!





Tuesday 24th - Another concentrated effort

Apologies again for the bias towards the Paintshop activities, but with another large Painting team in attendance and the need to get the project completed, inevitably there will be an excess of photos. To quote Paul of St Blazey again, it is currently very much the "25451 show" on Tuesdays, Thursdays and Saturdays.

However a range of other subjects to report first.

Please excuse the wide angle distortion, but I just had to capture the Mess Room scene with 17 of us attending, a very good turn out for a Tuesday. At least two more could have been in which would have made it a record attendance for this day.

Anyone visiting our galas will probably recognize a section of the yellow viewing area barrier set up at the north end of Platform 1. This is all part of the preparations for the Santa trains which start this coming weekend. I believe they are completely sold out.

Rake 1 complete with decorations and ready to run the Santa Specials, .........

.........  but without FO 3132 "Mary" which has one or two issues that need attending to and is in a desperate need of a repaint, especially the roof.


Derek continues the patch repairs to the Malvern side of the Shark van.


While inside the south veranda Paul continues the priming of the ceiling planks. Apparently these were not done when the roof was replaced during its last refurb.


Paul breaks open a new tin of primer and gives it a thorough stir.


Dave concentrates on sanding out the old triple-banded line on the Cotswold side of TSO 4406. Going into Chocolate & Cream will mean a two banded lower line so we need to remove all trace of the old one.


We had a request to get the new metal at the north end of TSO 4867 coated in Green Primer, so Keith gets that done.


Phil was back on his clean up of the stock of electrical connectors. 


I love this novel way of getting them painted.


Now nicely primed and ready for undercoating 


This is the final batch of main base sections of internal window framing for 4867. Having been brushed with wood preservative and now dry, Keith adds the Georgian Mahoghany wood dye. By the end of the day they had been given the first coat of varnish.


With his Works H & S hat on Roger has come in specially to get more records set up.

**************

Now back to the Paintshop for the day's progress with 25451. The photos are in the order taken.


There was still a lot of lining out to do on both sides. On the Malvern side Steve tapes up the top line on the south half to paint the gold band.


Down below Ian is adding top coats to the inside of the battery box. This is the box that had the new floor, hence the Dark Grey undercoat.


On the north half Phil is preparing the lower line for the gold band.


The Cotswold side is much further advanced. As such Stu is able to tape up almost the whole coach length for the lower black band.


Some of the windows on the Cotswold side south half need tidying up. As such Richard carefully adds white paintable sealant.


The next job is to tape the Cotswold side north end top line ready for painting the black band. With this done Richard now adds the Black Gloss.


Back to the Malvern side where Roger is adding the Gold paint to the line taped up by Phil.


Stu adds the tape to the south Cotswold side corner ready to fill in the vertical gap where the original demarcation tape had been positioned.


David on the last stretch of painting the corridor skirting and heating pipe covers. With the windowframes revarnished as well, the corridor already looks a lot better.


Later on he is carefully painting the demarcation zone gap on the Malvern side south end.


Richard is now taping up the Cotswold side upper line, again for the black band. The festoon of used tape is from the north half. The tape is removed as soon as painting has been completed for that section.


Stu finishes off the south doorway.


Later on, with the tape removed from the Cotswold side lower line, Stu does a bit of snagging.


The Cotswold side with the lining out almost completed. We need to do some snagging, especially with the black band under some of the windows where taping up directly under the frame can be tricky, but overall it's great to get the job done.


The Malvern side is rapidly catching up with Steve and Phil cracking on with their respective lines.


David finishes off the Cotswold side battery box.


Phil, having second coated the gold band on the Malvern side north half, now begins removing the two tapes. I started at the nearby end and we soon had the tapes removed. Tape is removed carefully from the lines, if necessary using scissors to cut small sections, to prevent potentially wet tape flying back on to the coach side.

So, still a bit to do, but it is seriously getting there. Hopefully attendance in the team will remain high and we can meet the requested deadline.


**************

To finish off a little cameo on the new key tags for our five brake coaches.

The bundle of part completed tags and the numbers required.

Now at Louise's home in Minchinhampton. Her sewing machine is quite sophisticated and includes an embroidery facility. First a practice run to check the size and colour - this is the largest font available.

It would have been great to have had the characters half as large again, and although Louise is quite capable of doing hand embroidery and doing it very well, it would take a lot of time.

Now for the five tags. Careful measurement to centralize the number location.


The required letters and numbers have been set up in the machine and stitching begins. 


The first one completed.

Back in Upholstery, the finished set laid out with the link stitching blacked out. Now over to the team to insert the key ring and finish each one.