Posts

Saturday 27th - We're back, and it's still hot

It was a very hot week, and so not only were trains cancelled, but the works were closed too. It really was just too hot to do any work. Apart from anything else, the paint would have dried before it even left the brush! But we were back on Saturday, although as the temperatures were still high we took it gently.


The big tie rod on the Mink D had a kink in it. I deliberately didn't take it out so it would still fit when we came to bolt it back on. I tried bolting it back on, and it didn't fit anyway, so Andy and Ken gave me a hand straightening it on the press. 


Now it fits! Looking for some gentle work in the still considerable heat, I went round with a box of split pins too on various bolts.


"Upstairs" Maurice and Paul carried on removing flaky paint from the underside of the roof.


A quick look outside saw Betton Grange on rake 2. Still pretty hot on there, but at least both steam locos out today had open cabs, deliberately chosen.


It had been a few weeks since I'd looked on progress in the saloon pantry, it's looking really good!


Then the usual occupational hazard of a blogger "Ah, perfect timing, hold this!" from Simon as we fitted the upper shelving unit.


Andy too found a gentle job for the morning, cleaning up a box of grotty bolts.


John had a nice little milling job with the V bar from the fly press got distorted and needed milling flat again.


Phil was overhauling some spare parts for gas systems I think.


25451 is coming along well, Alan had a big hole in the roof to deal with today, having removed the old patch repair.


On the other side Ian carried on with some initial sanding to remove the old waist lining.


Back in the paintshop, Graham was on varnishing duties.


Friday was extra time for me as guard and shunter doing a couple of deliveries. The first move was our latest arrival, TSO 3961 from Carnforth, which needed bringing to Winchcombe. It looks a bit of a mess, and truth be told, it is, external bodywork wise. But it's got a good underframe and bogies, and the interior is complete, and even better is a nice early example with wooden paneling and flying saucer lights. 


The return working was to bring the dogfish with the leftover type 1 back to Toddington to be used as infill for the platform extensions currently ongoing. In 30 degree heat, this was as close as we got to air conditioning! It was actually a pleasant breeze as we rattled along, but the shunting at either end was hot work.

Monday 22nd - Unexpected Announcement

 Another Carriage Clean, but this time a warmer day. So first job to walk through and make sure everyone was OK and say take care not to overdo it in the heat.

So first up were Chris and Peter starting to wash rake 1. Rake 2 in the sunny platform 2 already done. David was sorting the hose out.

Then Greg


With John M on holiday Lynn took on the job of toilet cleaner. Here she has just finished.


I passed Roger C and Val on the way through the train to find Steve cleaning the cage in the BCK.


Then Jane on window cleaning.


After that I went and got a GTech from the shed and used that the full length of train 2. John S was elsewhere using the Ghostbuster. Which brings me on to a text I received from Rich (our other Ghostbuster operative) on Sunday evening. He has been struggling with a hip problem for a while but it has now reached the stage where he has had to suspend carriage cleaning until he has a new hip. He is only just starting that queue so it is going to be sometime before we see him again. He hopes to continue RCS fish'n'chip duties for a short time. John S, our other Ghostbuster operative, had a very successful knee replacement last year but he is now awaiting the summons to do the other one. So no Ghostbuster users! We will have to give that some thought. Kath and Nick were also in today.

Knowing how hot it can get in the trains this time I took a thermometer with me.

Platform 1 (shadier platform in a morning) - "Mary" 29°C
Platform 2 Disabled coach. Shady side - 38°C
Platform 2 Disabled coach. Sunny side, on a seat - 45°C

After that it was tea break and the unexpected announcement came through on email. TRAINS CANCELLED UNTIL SATURDAY 27TH JUNE. That was followed by RCS staff removing stock from the train that would be out of date by Saturday. Just one of many tasks that needed doing to shut down the railway unexpectedly. 

On a totally different note, we were on holiday last week in Portsmouth, and amongst other things saw HMS Warrior. I had seen this before - when I was in the Sea Cadets and we saw it as a hulk in Pembroke, 65 years ago!


And of course the "Mary Rose". Most of you probably remember it being raised from the seabed in 1982. Lots to see, never enough time or strength in the legs!

Saturday 20th - A name and a face

It was very busy today with 25 attending, though obviously I wasn't able to record everyone. 

Many of the photos on the blog are simply snatched opportunities in between my own work and very much a case of being in the right place at the right time. So apologies to those I miss or for whom little is shown. Doing the blog is very much a job in itself, each posting usually taking several hours to produce, but it can be very enjoyable recording our day to day activities and the progress being made.

As well as being stored on my own laptop and backed up on USB, a copy of everything is also stored on a USB stick which is kept in the Works Office. This includes all the Wednesday photos taken by Gerry, as well as those taken by other members of our Works staff.

***************

So moving on to a very busy day and beginning with SO 4798.


Clive fitted the data plates at both ends, the south end requiring holes to be drilled in the new sheet metal.


Inside the south vestibule Robert (and Chris) fitted two lengths of corner beading. These had aleady been dyed and varnished.

For Alex it was very much a signwriting day, the first job being the painting of the shadows on the letters in the coach name.


Graham got going with the varnishing, applying the first coat to the south end on both sides of the connection.


Bob checks the back of the Cotswold side south door. Somehow the top section has been missed and hasn't had a fresh coat of varnish.


Half of the varnished south end. In the background Alex is finishing off his shadowing.


One of the door paintings complete with black border.


Bob is now well into varnishing that door back.


The finished name. I mentioned several times that it would be nice to get Christine in to photograph her next to it. And who should turn up?


It's lovely to name the coach after her. She was Head of RCS for 8 years, working tirelessly to keep the department running, and even now she is still involved.


She looks completely at home, finding the seat very comfortable.


Graham has moved round to the Malvern side to begin varnishing the upper half of the north end section. Basically we can varnish any section not being finished off by Alex today.


Bob let Graham have a good head start as the top half takes much longer. He then followed on doing the lower panel.


It was a hive of activity inside 4798 with Ian and Clive setting up more tables. I think Ian said at the end of the day that there was just one more to do.


A question was submitted in the previous posting about the spacer blocks not being dyed and varnished. Just to say that the outer side of the blocks will be visible and as such have been suitably treated.


The main Malvern side battery box cover is just slightly short, and when it and the top section are fitted, a small gap remains. The simplest solution is to expand the latter and as such Robert and Chris are cutting a narrow length of wood to attach to it.


The Malvern side north half with its first coat of varnish.


Still more for Alex to do on the sole bar on both sides, and then there will be the coach data at both ends.


With their varnishing completed for the time being on the Malvern side, Graham and Bob varnished the opposite side. Being a staff through route the barriers are essential.


What a wonderful sight! We love our loco fleet, but at the same time enjoy having visitors stay for a lengthy spell with us. We have had "Manston" for  quite a while, but she will be going back to the Swanage Railway, I believe in a few weeks time. Now we have a Black 5 to enjoy. A number of us have a particular fondness for these so this really is a treat.


3850 arrives with the Cheltenham train.


45110 gives the well known Stanier hoot and leaves for Toddington.


Down the yard in TSO 4763 Jenny is busy window cleaning.


She looks weary, but thanks Jenny for your efforts so far today.


At the south end of SK 25451 Alan cuts out another square of rusted panelling.


On the Cotswold side the window reinstated by Gerry and Ken on Wednesday.


The next one to come out - the holed area to be replaced is on the corner, just above where James is working to free up the frame.


"How's it looking?"


In fact both corners were bad.


James marks out the replacement for the right hand side before using the plasma cutter.


The left side repaired and awaiting the anglegrinder.


The cut out section on the right hand side .......


........ now repaired.

Alan has welded in the new piece of sheet metal and is now cleaning up the weld. This was then coated in Red Oxide.

Ken was rebuilding the connection from the south end of BSK 35308. The rubber bellows section has been bolted on, and with clamps in place he uses a grinder to slice off the excess rubber.



John is checking the wear of the wheel tyres under 35308 using a special gauge.


Later in the day the hiss of steam from the station and sound of a whistle from an approaching train has us rushing out to see the action.



The heavy metal bar of the folder is bent and needs replacing.


Andy is producing a replacement using a heavy piece of angle iron.


Phil's new racking in the storage area is coming along well, with the shelves now being fitted. A quick check while locking up for the day showed the completed unit in place with toilet tanks stored on the shelves.

It was just Jane and Laura in Upholstery today, busy making door stops. It looks like we are definitely going to include this new item in our shops.

On returning towards the end of the day I discovered two partly completed ones (on the left), so quickly made up a montage with the two completed and the tray of gravel used for the weight in front. 

Paul W captured Alex washing up. Could this be a first?!



Our indefatigable Rose has once again brightened our day with another lovely display. She had spent much of the day on the office computer doing our admin work. 

I'm not sure what will be recorded next week. The forecasted heatwave with temperatures in the 30s and "feeling like" nearly 40C is keeping many away. It will be good to return to more normal weather for this time of year. We have much to do!