Posts

Showing posts from 2026

Tuesday 3rd - A busy day and an Autumn Gala


A busy day, starting off with Paul cleaning up another heavy bolt from the Shark Ballast Plough van and making good use of the existing parts wherever possible.

[Photo : Paul E] The cleaned up and repainted planks are now going back on the Cotswold side of the van.

[Photo : Paul E]  Derek redrilling the holes in the top support. Lovely bit of blue sky!


[Photo : Paul E]

[Photo : Paul E]  Dave was back to giving TSO 3961 an overall sanding.


[Photo : Alex]  The Malvern side of SK 25451 with the first top coat on the main cream and crimson sections done by Alex on Saturday.

Stu had previously done a first rate job with the first coat of crimson on the Cotswold side and as such we reverted to hand flatting with 240 paper, though it hardly needed it. A general keying would have been good enough, but keeping in with our new regime we soldiered on.


While Stu, David and I dealt with the crimson panel, Ainsley cleared the windows of any paint drips.


This was followed with the flatting of the cream panels between the windows, and the doors and end sections.


On the Malvern side there are still windows to top coat, so Ainsley got going with those.


That south connection door will be ready eventually. It will need a second top coat so Roger carefully keyed it. He then completed most of the other internal connection painting, leaving just the chequerplate to paint with Hammerite.


David completed the internal connection painting at the north end, including the chequerplate.


Phil was busy making more patresses for mounting electrical connections. The belt sander nicely completes the job. They were later taken to the Paintshop trestles where Keith primed them ready for painting. 


The seemingly endless job creating new hardwood internal window frames for TSO 4867 continues with Robert and Chris steadily producing another batch.



A good batch dyed, fully varnished and ready for collection on Wednesday. The most recent ones have been coated with preservative and await dyeing.


Tony is removing old cracked paint and filler around this Cotswold side window on 4867.


Not sure where this sandwich board is destined or what will be signwritten on it, but Keith is painting it with matt black as requested by Alex.


While in Upholstery and making use of their nice clean work table to cut more rag, Chris appeared and placed this special display stand he had made at home.


In answer to my question about what it was for, he quickly provided the answer.


Rose later appeared and set it up completely with six spectacle cases. What a brilliant idea! 
Apparently a display stand has been made for the keytags but we couldn't find it. It may of course have already been taken to one of the shops.

***************

A very enjoyable day in the Forest

The weekend of 31st Oct/1st November saw the excellent FODR Autumn Gala take place. Everything ran to time and with two guest engines as well as their existing active steam fleet, double heading, a short goods train, and brake van rides, there was a lot of action to enjoy.


Pam and I went down there on Saturday. There was plenty to see while we were sat in the first train of the day hauled by the WD Saddletank 152 "Rennes", waiting to depart Norchard Low Level and go to Lydney Junction. The guest engines, the Standard 4 tank 80078 and the LNWR Webb Coal Tank 1054 (BR number 58926), were at the shed being prepared for the day's running.


Perfectly timed for us, the Coal Tank passed by and very obligingly stopped almost opposite our window. It would be coupling on to Set 2 after we had gone.


At Lydney Junction the GW Pannier Tank 9681 was waiting for us as it would be doubleheading the train back to Norchard and on to Parkend.


192 runs round the train ready to couple up.


Have travelled to Parkend and back, Pam and I had  a cup of tea and then a good look around the excellent museum. There are two paintings in there I would love to own, a pannier tank with a short goods train crossing the river bridge at Lower Lydbrook and Rob Rowland's excellent portrayal of a crimson and cream GW Railcar crossing Lydbrook Viaduct. 


During the main running period Norchard Low Level becomes the home of the brake van rides, all included in the cost of the gala entry fee.  As with last year when we came down for the Autumn Gala, the Saddletank "Uskmouth 1" was in charge and provided a very enjoyable interlude to the main train running. 

It was a decent length ride, running almost as far as Middle Forge where the low level and high level lines meet.

The guard displays the green flag on the return to Low Level. We enjoyed the ride so much that we happily had another run later on, and would even have had a third had time permitted.


With our tour of the museum and lunch break we missed travelling on the trains being hauled by 80078 and 1054. It was however great to see them in action. 80078 starts off from High Level with the train for Parkend.



9681 and 152 pull away from High Level with the northbound goods train.


We watched "Uskmouth 1" leaving with another brakevan trip and on its return had our second run on board. It proved to be a very popular feature in the gala and nearly always had a steady number of passengers.

Our final run to Parkend was behind 152. We could have waited there for the next train which was doubleheaded by 80078 and 1054, but it would have been a very long wait. We had anyway had enough for the day so remained on the train and on return to Norchard we set off for home.

We will certainly be back for next year's Autumn Gala.

Monday 2nd - Autumn Comes.

 Rake 2 in P1 and rake 2 in P2. This is just north of the Stow road bridge. Don't the rails rust quickly!

As usual I started my day with the vacuum in "Mary". Good to see it has been well used. Reports from last week say the trains were very busy with half term visitors.

Before

After


Nigel Ghostbusting the window ledges

And Steve again on luggage racks


Somebody has moved Toddington....


The only team member not with us today was John S, still in the final weeks of recovery from a replacement knee operation. But Rich picked up a Ghostbuster for the first time since his hip replacement. The others were Chris, David, Greg, Jane, John M, Kath, Lynn, Nick, Peter, Roger C, Tim and Val

Last Thursday Kath and I were part of the team on an extra Teddy Bear Thursday, with a Halloween theme. It was pleasing to see the trains so busy.







Tues 27th - Thurs 29th - A bumper bundle

One bumper posting for the mid-week activities to make way for the special Weedlink post.

Please note that Weedlink has now been added to the Special Articles section in the Blog's Main Menu so will be readily accessible for future viewing.

In answer to St Blazey's comment at the end of the Weedlink article, just to say that there is a secured chair on board the wagon. I thought there was a photo which included it but so far have been unable to locate it

**************

Tuesday

We had 12 attending on a day of mixed weather, which in the end became very pleasant. 


With most, if not all, of the pieces for the inner parts 4867's window frames now made, Robert and Chris have moved on to the outer parts.


Newly made on the bench are ( l to r ) two inner sections, a large outer base section and 4 or 5 outer side pieces.


Keith adds a second coat of varnish to the four inner sections, three of which are for 4867, with the fourth for Alan on Thursday for a repair, presumably in Rake 3.


Keith paints the cleaned up ceiling lights, the bowl section in White gloss and outer rim in Silver Hammerite. In the middle are the frame sections previously shown in the Woodshop.


Paul top coating the planks from the Shark Ballast Plough.


Where the repainted blanks will end up.


On to 25451 where Stu is applying the first of the Crimson top coat to  Malvern side south end. I was doing a final bit of hand flatting on the north half.


Richard gave all the Malvern side windows a second undercoat.

The Orange Brown top coating on the south connection sliding door failed to cover marks underneath, even with two coats. So the decision was made to apply Cream undercoat over the whole door to provide a consistent base for further top coating. Roger keys the paint surface and then repaints the door.




From the south end the initial top coating is looking good. The temporary barrier will prevent anyone accidentally passing too close to the wet paint.


With the tower brought back round to the north end, Ainsley paints the rain cover and nearby pipework, and then the bellows.


Stu takes a well earned breather. Having almost completed the first top coat on the lower section, he has done a great job today.

******

During the afternoon I gathered the team together for a demonstration of our new Mirka dust free sanding system, showing them how to both set it all up and, more importantly, carefully dismantle it.


Richard has a go with the circular sander. It's very light to use and has adjustable speeds. Assoon at it starts the vacumm unit springs into life and completely draws in the sanding dust. Perhaps I should say meshing dust as of course the abrasive surfaces that are mounted are an abrasive mesh.


Now Keith has a turn. 


The team were very impressed and all very pleased that dust masks were not required.

The Mirka system was supplied by Restorate Ltd (www.restorate.co.uk) and kindly funded by the GWRT from the Peter Bennett Fund. A number of boxes of the mesh sanding pads ranging from 60 to 240 grade were kindly donated by the firm.

Sam from Restorate had previously visited to demonstrate this excellent system and at the time several of us had a try and were extremely impressed. This was something we had to have, so we are very pleased that we now have it to use.

With today's top coating on the Cotswold side, Stu couldn't paint the centre door as it still needed flatting. I would have happily used the new system on the door with no worries about the possibility of dust landing on the wet paint on either side, because there wouldn't be any! It wasn't done simply because we were more worried about getting paint on either the sander or associated piping and power cable.

******

After the morning's showers the day became very pleasant.


Making the most of the Black 5 while it is still with us. It is certainly popular with our passengers. Granted that it is half term and as such we expect to get more passengers, this train had very well filled carriages. I wonder how the take up for the special Fire and Drive day with 45110 is faring? 


The train heads back to Toddington and Broadway.


******


The late afternoon sun and lengthening shadows. While FK 13326 in Rake 3 stands out, on the right SO 4798 "Christine" positively shimmers!


SK 25451 is also beginning to shape up very nicely. Roger black glossed both the connection interior and face plate and it now really stands out with the rest of the south end nicely undercoated.


I caught 45110 again on the final run of the day. With the hour now on the winter setting it will soon be dark.

**************

Wednesday

As always, grateful thanks to Gerry for Wednesday's photos.


Upholstery are as busy as ever with Eve working on another stripped down seat base from TSO 4867, ...........


.........  Ceri making another bag, .........


.........   and Laura doing the essential stocktaking.


Really back to basics with the coach base and bogie of TSO 4867 very much in view. Neil test positions a new doorway threshold.


Neil and Simon positioning a new floor cross beam.



Simon fitting side pieces to the replacement top hat crossmember recently welded in by Nick.


Trevor is fitting new supports for the side panelling.


Rex and Bryan continue the internal rebuilding of the windows.


With the all-round wood base securely fitted, the first of the internal parts of the window frame has been drilled and now ready to be secured.

In the Barn the Cotswold side toilet window is now being reinstated by Gerry in the repaired section at the south end of TSO 4406.


The frame has been cleaned up, but will be fully secured before the glass is reinstated.


The GW Inspection Saloon remains elevated on the jacks while the heating system pipework is being rebuilt by Ken.


Two views of some of the rebuilt pipework.



*************

Thursday

Many thanks to Roger for the extra photos. 

Beginning today with the Indoor Gang making window repairs in SK 24949. The repair was to the base section of the inner frame.

 
[Photo : Roger]  Alan and Geoff prepare the screw holes in the metal frame.


[Photo : Roger] 

 
[Photo : Roger]  The new section of frame is temporarily secured and the screw holes marked for drilling, .................
 

[Photo : Roger]   ......... and then taken back to the Workshop to get the holes drilled.

[Photo : Roger]  Now back in 24949 Alan inserts all the screws.


[Photo : Roger]  Job completed with the replacement fully secured. The overall outer frame will need to be fitted next.
 
The next job was in FK 13326.
 
 

I took this photo just over a week ago showing the centre panel and seat side removed.

[Photo : Roger]


[Photo : Roger]  The repairs to reinstate two small side tables were completed.

 [Photo : Roger]

Now back to the Barn where Alan has prepared the whole of the left hand side of TSO 4406's south connection ready for attaching one of the two remaining half ends purchased some time ago from South Devon Railway Engineering.


 

Also at the south end Gerry is preparing to secure the reinstated toilet window frame.

Rex is cleaning up and checking the many screws and related window frame fixings.

Jeff continues the dyeing of the remaining sections of window frame. With the spirit dye drying quickly, he was later to get them all varnished. 

Including Jeff, we had a very good turnout for the Painting team today with seven of us attending. As such a lot was achieved with SK 25451 without treading on each other's toes.

Trying the new Mirka sander for then first time, Martin flats the undecoat on the Cotswold side centre door.

Phil later uses it to flat the centre cream panels on the Malvern side north end. It was also his first time. Both Martin and Phil were very impressed with new equipment and enjoyed the freedom from having to mask up.

Tony painted on a second coating of the Express Red undercoat on the main panel from the centre door to the south corner on the Malvern side.

Martin now adds the first top coat to the centre door.

Tim keys the south connection door.

Martin has now moved round to the Malvern side to begin top coating the windows.

With the keying done Tim now applies the Orange Brown top coat. No surprise that the result is proving to be much better. I should have suggested a full undercoat to begin with - some paints cover well and you can get away with a lot, while others don't take to shortcuts.


David was busy adding Black Gloss to the north end.

With the door painted Tim moves on to doing the same at the south end.

David is now very well into his painting and should complete this end, bar the bit directly over the connection for which the scaffold is best to use.

 Tim is also well into his end with the Cotswold half completed and the connection currently receiving attention.

The Malvern side completely undercoated with top coat going on.

Tim completed the Cotswold half of the south end and managed to get the Malvern half done as well.