Posts

Showing posts from February, 2025

Thursday 27th - A major milestone achieved

After yesterday's shunt to complete the final formation of Rake 2, our shutdown period was officially over. Not so many attending today, but a major milestone was achieved by the end of the day.

Over the past couple of days the police and army have been conducting an excercise using Rake 3. Alan, Geoff and Paul take a few moments to watch the activity.

With Stu driving the 03, the eight coach Rake 1 passes by on its return to Toddington. Rake 2 followed afterwards.

Rake 3 will be set up in its final configuration in preparation for Race week, after which RMB 1876 will be made ready to come into the Works for maintenance and repainting. 1876 was on our side of the yard and so not involved with the police/army excercise. Paul walked through the coach looking at various aspects requiring immediate repair by the Indoor Gang - Alan, Geoff and Roger.

It was just Bryan working in SO 4798 today, preparing more internal window frame. The milling machine is being used to produce counter bores in which to insert the special nuts. When the screws are in turn inserted the piece of frame is tightened against the window. These all get retightened when fully in place which stops leaks.

I didn't catch Derek working on the Monster van. This was the only other activity not involving RBr 1675 which had quite a concentration today.

With the underframe dust removal completed, it was now the turn of the roof. We can reach almost all the roof from our large scaffold tower, especially when extra metal piping can be added to the existing lengths when vacuuming. Phil begins the job at the north end.


Bob Mack's excellent painting is once more revealed. Far better to get this done inside than leave it for the wind and rain to remove.


Alan, Geoff and Roger did some final work on the corridor connection doors. 1675 will spend its time in the middle of the train, so both doors will remain permanently open. Despite this both must be able to be closed and locked correctly. I later returned to painting the door edge.


The south end door originally did not close properly, but previous adjustments made by Robert and Chris ensured that it is now fully functional. Paint repairs are in progress, and now Roger completes the job making some final adjustments to the closing and then refits the door catch to enable it to be locked open.


The team also completed the fitting of some missing sections of skirting. 


Meanwhile main painting continues with Martin working on the Malvern side from the south end, adding the first coat of GW Cream. Some of the windows on this side have already been given an initial top coat, presumably done as a fill-in job when nothing else was available.




Bob started from the north end. However, with a tin being emptied following removal of a skin, it was definitely desirable to dig out the supply of old tights!


Bob started at the north end and the first coat of cream was completed.


Today the two Richards and a visiting contractor conducted the commissioning of the batteries and battery inverter in 1675. I am very pleased to report that the testing was successful. All the electrics are working as designed and as such a major milestone has been achieved.

Tuesday 25th - A very special day

Today was a very special one with the Memorial Service for Bob Mackintosh, always known as Bob Mack, and one of the original volunteers on the Railway and in his latter years regularly helping in C&W.

The service booklet was beautifully produced and completely based on the Railway.


Toddington Church was packed to the point where quite a few of us were sat in the chancel. Sadly because of the acoustics and echoing we could hear almost none of the readings, but it was still good to be there.


Roger took the above with some great photos displayed.
 
The Railway Recollections read by Richard Johnson, Head of C & W for 18 years and then, until recently, our PLC Chairman, vividly detailed what a huge part Bob played in the early days of the Railway, taking on so much responsibility in its organisation and running. Richard had in effect known Bob for 44 years, almost literally from the beginning, so his anecdotes were many and varied, many of them humerous. For a lot of us joining in the 2000s, Bob was still heavily involved as a regular Duty Officer, Guard, Signalman, the PLC Finance Manager, lineside clearing, and with C&W one of our regular roofers. Both RBr 1675 in the Paintshop and SO 4798 in the Workshop have roofs that are already fully painted thanks to Bob, and in fact the first roof we will have to tackle without his excellent work will be RMB 1876 when that eventually comes into the Works.
 
The reception was held in the Cotswold Halt cafe at Toddington Station, with the room almost packed out with so many attending. An excellent buffet had been laid out with hot and cold drinks available.
 
Overall it was a lovely memorial for Bob and our thoughts go out to Gillian, Alistair and Jane.


**************

Many thanks for all the recent comments and kind thoughts that have been passed on in the blog with respect to our efforts.

In answer to the Cornishman magazine anomaly recently highlighted:

I noticed in the latest edition of 'The Cornishman' that it was reported the tables and chairs had been installed in RBr 1675. I don't know if it's my increasing age, but I can't recall seeing any photos of this in your usually comprehensive C&W Blogs. Did I blink and miss them??
A Pettifer

When writing the Carriage & Wagon report for The Cornishman it is not uncommon to have to anticipate events or as we like to say "write for the future". Our report in the Spring edition of the magazine was written in mid-December, so with the saloon in 1675 basically completed, it was not unrealistic to assume that by mid-February the tables would have been installed, with the chairs rapidly following. However this was not to be and the saloon currently remains empty. The likely cause for the delay will be the many repairs needing to be done to our coaches during the shutdown period. With shutdown almost ended and services restarting this coming weekend, we will be able to fully return to the refurbishment programme.

***************

Now on Tuesday's efforts.  Grateful thanks to Paul E. for the extra photos taken while I was attending Bob Mack's memorial service and reception.


Richard completed the painting and varnishing of the repairs previously made in the corridor and south vestibule in FK 13329 by Simon and Alan.


Part of one of the new veneer panels and surround, stained and now given a coat of varnish.

The repair to the water-damaged panel in the south vestibule. 13329 has been added to Rake 1 as the 8th coach for the four days of the Cheltenham Race meeting.

[Photo : Paul E.]   In the Workshop Bryan drills holes in the final compartment windowframe on the Malvern side of SO 4798. Ainsley also worked on the coach, doing some more general sanding of the Cotswold side.


While Richard pours back some unused paint, Keith primes a number of large bolts which are either for the MICA van or Open C wagon.
 

 [Photo : Paul E.]   The bolts dried quickly enough to be further painted.
 
 

[Photo : Paul E.]   Painting the underframe of the MICA van was done by both Maurice and Paul..

 

[Photo : Paul E.]


[Photo : Paul E.]


[Photo : Paul E.]   Just outside the Paintshop on the Works siding, Maurice is working on one of the axleboxes on the Open C wagon.

When RBr 1675 arrived in the Paintshop it was covered in dust, which meant a major clean of the body sides had to be done before we could completed the remaining bits of undercoating. The underframe, headstocks and corridor connections are as bad and as such we needed to get these similarly vac'd and wiped over, especially with the top coating which has now been started. Ian took on the job and literally circumnavigated the coach, leaving just the underframe elements that were dirty - decisons will be made as to how much of these are to be cleaned and even painted.

[Photo : Paul E.]  The final major dedusting job will be the roof.

The bogies must have been gritblasted for them to have been painted up this much. There will be work to do on them when the coach goes into the Barn and on to the jacks.


Ainsley also went around 1675 adding little tape bonnets to the tops of the door hinges to prevent them being painted. We, the painters, haven't done enough of this in the past, hence the justified grumbles by both the Door and Friday Maintenance teams when it comes to greasing the hinges..


Saturday 22nd - Nearly spring, nearly steam

 It was the last weekend to get everything sorted before the beginning of the new running season, with services beginning 1st March. It also felt like Spring might be not too far round the corner too, as it was quite a pleasant day weather-wise.


Which was just as well as the shunting team had a lot to do to put rake 2 together. First move of the day happened to be to put all 4 crimson and cream coaches for the rake together. This was just temporary for now but I couldn't resist the shot.


As the sun broke through proper there was a lot of to-ing and fro-ing, Chris and Robert come out to watch proceedings.


Definitely appreciating the nice new bright livery in the sun. These 3 definitely are staying together, looking south there's a choc & cream RMB before the last crimson coach for now, but plans are in place to steadily work through replacements for the rest of the rake this year.


All important on a big shunt is to have a signalman who's on it, John certainly had to work today to keep up with it all, but signalmen tend to like all the unusual moves, much more interesting than just an ordinary day.


One of the last moves to take a few coaches from set 3 off the end of the now formed set 2, Tony pulls the buckeye chain as Andy gives the signal to pull away.


There was god progress with wagons today too, starting with the Mica, Robert and Chris continued the woodwork fettling, with all the roof edging bits done as far as can be until we get the canvas on.


After the test fitting of some of Nick's new steps, we realised the bolts needed some larger washers behind to firm everything up. Maurice on the outside...


And Paul on the inside.


The wheels also got painted black. The springs have now been taken away for refurbishment.


We were missing one of the retaining pins for the springs so John kindly turned us a new one.


The Open C also saw good progress, Ken virtually completed the through pipe with the second elbow joint.


Cutting the last bit to length.


Dave caught me with the mag drill drilling the holes to bolt the hinge straps back on. Here lining up for the next hole before drilling.


More or less ready for some timber now, although we still need to get that dodgy wheelset out and sort the seized buffers. There was some talk about getting it in the currently empty barn for a bit (ok mainly talk by me...)


With the RBr in the paintshop, it was time to get cracking with that again. Dave worked his way along cleaning dust off and Bob followed behind with the first of the topcoat, doing the chocolate band along the top.


A few bits still needed undercoat and Jeff did the honours here.


Robert also took a look at the end corridor door which wasn't closing properly - I think it is now.


It was a hive of activity in upholstery with several new members, judging by the moquette I'm guessing these were seats for 4798.


Speaking of, Alan was inside 4798 fitting various bits of wooden trim in the North end saloon. I later followed on with some woodstain. A splash of varnish and this saloon will be nearly finished and ready for tables/seats refitting.


At the South end there's still lots of metal work going on. The lower panel below the toilet window was badly warped, so the decision was taken to replace it. Stuart drilled out the door hinge to provide access.


James soon had the wobbly panel cut out, and provided the photo to prove it.